Multi‐criteria optimisation approach to increase the delivered power in radial distribution networks
Abstract
This study proposes a new methodology to increase the power delivered to any load point in a radial distribution network, through the identification of new investments in order to improve the repair time. This research work is innovative and consists in proposing a full optimisation model based on mixed‐integer non‐linear programming considering the Pareto front technique. The goal is to achieve a reduction in repair times of the distribution networks components, while minimising the costs of that reduction as well as non‐supplied energy costs. The optimisation model considers the distribution network technical constraints, the substation transformer taps, and it is able to choose the capacitor banks size. A case study based on a 33‐bus distribution network is presented in order to illustrate in detail the application of the proposed methodology.
Nomenclature
-

-
- individual objective
-

-
- satisfaction level of
solution with respect to the ith objective
- satisfaction level of
-

-
- desire reference level of the ith objective
-

-
- maximum of individual objective
-

-
- minimum of individual objective
-
- Φ
-
- set of non‐dominated solutions or plans
-
- r2
-
- lower bound for real expected repair time (h)
-
- r3
-
- upper bound for real expected repair time (h)
-

-
- average of repair times (h)
-
- tα/2
-
- t‐distribution
-
- n
-
- quantity of repair times
-
- s
-
- standard deviation
-
- μ
-
- real expected repair time (h)
-
- λ2
-
- lower bound for interruption rate (interruptions per year)
-
- λ3
-
- upper bound for interruption rate (interruptions per year)
-

-
- chi‐square distribution
-
- λ
-
- interruption rate (interruption per year)
-
- m
-
- action type
-
- ij
-
- component from bus i to bus j
-
- Z1
-
- investment objective function
-
- Z2
-
- non‐supplied energy (NSE) objective function
-
- I.R.R.
-
- internal rate of return (%)
-
- NE
-
- total number of system components
-
- Sij
-
- power flow in component (line) ij
-
- λij
-
- interruption rate of component ijth (interruption per year)
-
- rij
-
- repair time of component ijth (h)
-
- Nm
-
- total number of actions for repair time reduction
-

-
- cost of repair time reduction in monetary units (m.u.) for component ijth with action m
-
- Xij, m
-
- decision variable {0,1} for component ijth with action m to reduce repair time
-

-
- annual cost of repair time reduction in monetary units (m.u.) for component ijth with action m
-

-
- NSE cost in monetary units (m.u.) for component ij
-

-
- final repair time for component ij
-
- NSEFinal
-
- obtained NSE (kVAh/year)
-
- NSEMax
-
- threshold for NSE (kVAh/year)
-
- CRF
-
- capital recovery factor
-
- BNF
-
- Monetary savings
-
- dr
-
- discount rate
-
- t
-
- lifetime project
-

-
- generated active power at bus i
-

-
- active load in bus i in p.u.
-

-
- reactive load in bus i in p.u.
-
- Pi(v, δ)
-
- active power injections in bus i in p.u.
-
- Qi(v, δ)
-
- reactive power injections in bus i in p.u.
-
- a
-
- bank capacity
-

-
- reactive power output by capacitor banks in bus j
-
- Wj, a
-
- binary decision variable (0, 1) to install a bank capacity (a) in bus j
-

-
- reactive power (a) installed in bus i
-

-
- lower limit of generated active power in bus i
-

-
- upper limit of generated active power in bus i
-

-
- lower limit of generated reactive power in bus i
-

-
- upper limit of generated reactive power in bus i
-

-
- lower limit of voltage magnitude in bus i
-
- Vi
-
- voltage magnitude in bus i
-

-
- upper limit of voltage magnitude in bus i
-
- Sij(v, δ)
-
- apparent power flow in line ij in p.u.
-

-
- rating power limit of line ij
-
- tapmin
-
- lower limit of transformer tap
-
- tap
-
- transformer tap
-
- tapmax
-
- upper limit of transformer tap
-
- Δrij
-
- repair time variation for component ijth using a repair time reduction action
-
- m.u.
-
- monetary units
1 Introduction
Over the past few decades lots of efforts have been devoted to the distribution systems reliability assessment. Reliability is the ability to deliver electricity to all delivery points within acceptable levels of quality, in the desired amount and at the minimum cost. Obviously, these are conflicting goals, because increasing the quality and quantity of the energy provided to customers will necessarily increase the investment cost in networks, as well as the operation cost [1]. Network planners and operators must find the adequate balance taking into account the uncertainties of future conditions. The reliability criteria can be deterministic and/or probabilistic, however, in both cases a consistent database and an exhaustive statistical analysis of all the available information are needed such as interruption rates (λ) and average repair times (r) of distribution system components. Moreover, maximising the reliability in distribution power systems involves minimising the unserved energy, and therefore load curtailment.
There are two types of uncertainties in distribution power systems: randomness and fuzziness [2–5]. It is well known that interruption frequencies or interruption probabilities of distribution overhead lines are related to weather conditions [2, 3, 5–7]. Weather conditions are usually described in fuzzy words. Each weather condition (rain, wind, storm etc.) can be categorised into different degrees (such as heavy, medium or light rain) [2–5]. This classification is obviously vague or fuzzy. Interruption frequencies or interruption probabilities of distribution lines are also caused by environments (such as tree falling or animal activities) and operational conditions (such as load levels). It is very difficult to distinguish exactly the effects of these conditions on the outage data of individual components using a probability model, since there are little or any statistics available. Some utilities do not have enough statistical records, but they may have a good judgment on the range of outage parameters (such as repair time). A fuzzy approach allows obtaining adequate models for all these cases [2–5].
Unlike transmission systems, which are looped, distribution networks are usually made up by radial feeders. The most important consequence of radial feeders is that many customers can be affected by the interruption of a single component. The adequacy is represented by reliability indices such as average interruption rate λ, average outage duration r, and the annual outage duration U. These reliability indices are load point indices and they are of crucial importance for reliability studies. The average outage duration and the interruption rate can be reduced by network configurations, suitable location of substation, feeder length, and by increasing fault avoidance and corrective repair measures. These measures try to modify the interruption rate and repair time of each segment, improving the system reliability. Repair time and interruption rate modifications may require additional efforts which are associated with additional expenditures.
A technique for optimal reliability design in electrical distribution system was developed by Chang and Wu in [8]. This technique solved a non‐linear optimisation problem based on polynomial‐time algorithm.
A value based on a probabilistic approach to design urban distribution systems for determination of the optimal section length for the main feeder, number and placement of feeder ties, feeder and transformer loadings is proposed in [9]. A genetic algorithm approach for reliability design of a distribution system is presented in [10]. The objective function contains the investment cost, and the system interruption cost. System interruption rate and average outage duration at load point are considered as constraints. Louit et al. [11] presented an algorithm for determination of optimal interval for major maintenance actions in electrical distribution networks. Comparative case studies for value‐based distribution system reliability planning are present in [12]. An algorithm for optimum location of distributed generation (DG) in a distribution system based on reliability considerations was proposed in [13]. Arya et al. [14] proposed a methodology for reliability enhancement of radial distribution system by determining optimal values of repair times, and interruption rates of each section. A set of composite models for distribution system reliability evaluation that may be applied to non‐radial type networks was proposed in [15]. In [16], a three‐stage method for planning a power distribution system is proposed in which the substation optimisation, the number of feeders with their active route, and the node reliability optimisation are included. Chandramohan et al. [17] presented the minimisation of radial distribution system operating cost in the regulated electricity market via reconfiguration. Arya et al. [18] presented an analytical methodology for reliability evaluation, and enhancement of distribution system having DG. In [19], Ferreira and Bretas used a non‐linear binary programming model for reliability optimisation of distribution systems. In [20], the authors proposed an evolutionary algorithm for distribution feeder reconfiguration. The problem consists of minimising the power loss, operation cost of DG and non‐supplied energy (NSE) simultaneously. The considered constraints including the radial structure of the network, line thermal limits, transformer capacities and bus voltages are within their admissible ranges in this approach. Canizes et al. [5] presented a methodology which aims to increase the probability of delivering power to any load point of distribution networks by identifying new investments in distribution components not considering the network technical constraints. The proposed methodology uses a fuzzy set approach to estimate the outage parameters, and the investments aims to reduce the components interruption rates and repair times.
The references cited above do not have considered a way to increase the delivered power considering investments actions in order to reduce the repair time of the distribution network components, and all the technical network constraints.
Hence, this paper proposes a new and innovative methodology for increasing the delivered power to any load point of the distribution network, by identifying new investments in distribution components, while minimising the costs of those investments, as well as the cost of the NSE (multi‐objective problem). The investments aim to reduce the components repair time. The repair time reduction can be obtained by increasing the operation personnel, upgrading the automation system, improving the communication system and so on. The proposed methodology is a weighted AC optimisation model based on mixed‐integer non‐linear programming (MINLP) using the Pareto front technique [21, 22]. A case study based on 33‐bus distribution test network [23] is used to demonstrate the proposed methodology.
Since the presented problem is a multi‐objective optimisation problem, it requires a multi‐objective method for solving. This paper utilises a Pareto‐based approach, which can obtain a set of optimal solutions instead of one [24].
This paper is organised as follows: Section 2 introduces the fuzzy set membership models for outage parameters. Section 3 presents the proposed methodology to increase the delivered power by reducing the NSE in radial distribution network. Section 4 presents the case study and the discussion of the obtained results. Finally, the most relevant conclusions are duly drawn in Section 6.
2 Fuzzy set membership models for outage parameters
Each outage model is characterised by the following parameters – interruption frequency and repair time; interruption rate and repair rate; transition rates between multiple states; unavailability or forced outage rate; and standard deviation.
These parameters are the input data in risk evaluation, and they can be estimated from historical interruption statistics.
Most of the data collection systems provide the interruption frequency or the unavailability and repair time. Usually, the interruption rate and the repair rate are not directly collected, but they can be calculated from the interruption frequency and repair time [2–5].
(1)
(2)
(3)
(4)
(5)
(6)
(7)The use of the centroid of the function obtained by the gravity technique is an appropriated approach, and it is very similar to the weighted mean used in the probability theory, used for the defuzzification of the outage parameters. This technique finds the balance point by calculating the weighted mean of the membership functions.
3 Multi‐objective optimisation
When different incommensurable objectives with conflicting/supporting relations or without any mathematical relation with each other are considered, an appropriated tool like multi‐objective optimisation must be used in order to deal with this problem. Usually it is not possible to obtain an optimum at which all such objectives are optimised. Thus, the Pareto front method can be used to characterise the solutions from the multi‐objective problem. Pareto front optimal method is also known as non‐inferiority or non‐dominancy method [22].
3.1 Satisfying decision making
The decision maker's judgment to select the final solution has a subjective imprecise nature, thus a method to support its decision can be necessary. Fuzzy satisfying method can be used to select the preferred solution among non‐dominated solutions obtained in optimisation stage. To the decision maker it will be asked to determine its imprecise goals for each objective. As a result, the final solution will be found. Since the trade‐offs between each objective are determined in the first stage, one can expect a much reasonable judgment from decision maker comparing to prior methods [25].
After non‐dominated set determination, it is desirable to obtain a flexible and realistic solution that represents a trade‐off between different objectives [26]. Fuzzy satisfying method due to simplicity and similarity to human reasoning is of great interest. Fuzzy sets are defined by membership functions, which represent the degree of membership in a fuzzy set using values from 0 to 1. Fig. 1 presents a linear type membership function, which will be used in this work.

Linear type membership function (adapted from [25])
if
and not satisfied if
. Equation (8) presents the model used for all objectives
(8)
of each objective. To obtain the final solution a method called ‘minimax’ [27], have been applied. Thus, the following optimisation problem is used:
(9)4 Proposed methodology
The following proposed method when compared with the existence works, considers a technique to increase the delivered power, i.e. reducing the NSE. The technique deals with investments action in order to reduce the repair time of the distribution network components, and all the technical network constraints based on deterministic formulation. Thus, the proposed methodology minimises the investment cost, as well as the NSE cost in radial distribution networks. This methodology aims to maximise the power availability in each load point of this network type. A scheme of the proposed methodology is shown in Fig. 2.

Diagram of the proposed methodology
The proposed methodology has five main aspects, which are presented in more detail as follows.
4.1 Database
A consistent database creation and an exhaustive statistical analysis of all available historical data (such as repair times, number of interruptions, and number of repairs) are an important issue for the proposed methodology.
4.2 Target for NSE
(10)4.3 Fuzzy logic functions for r, λ and U
Several effects such as weather conditions, environmental, and operational conditions are very difficult to distinguish precisely on the outage data of individual components using a probability model, since there are little or any statistics available. Usually, utilities do not have enough statistical records of outage parameters. As a result, the fuzzy set approach allows obtaining adequate models. Equations (1)–(6) allow determining the membership functions for repair times and interruption rates of all distribution system components. Hence, membership function of unavailability can be calculated by (7).
4.4 Weighted AC optimisation based on MINLP
Considering investment minimisation and NSE cost minimisation the problem turns into a multi‐objective optimisation problem which is more complicated rather than a single objective of the optimal power flow (OPF) problem. Also, the multi‐objective optimisation problem has a greater search space than the single objective problem.
The proposed methodology can give to the planner the possibility to decide what objective is better for him depending on the pursued goal. The Pareto front technique can be a useful tool helping the planner to choose the more convenient preference. The Pareto front technique is generally used to solve conflicted objective function [28]. In the proposed methodology, the goal is to improve reliability, minimising the NSE, which is improved by investments in the network. Thus, conflictive objectives are present (maximise reliability and minimise investments).
An MINLP using the weighted Pareto front method is developed as it can be seen in (11)–(26). This mathematical model is applied in order to identify the distribution network components, in which investments allow increasing the delivered power to every load point in the considered network. The weighted technique is used to obtain the non‐dominated solutions. A set of weights randomly generated are used to construct a set of feasible optimisation problems.
The investment aims to achieve a reduction in repair times of distribution networks, while minimising the costs of that reduction as well as the minimisation of the NSE costs. Hence, a multi‐objective problem can be developed.
The repair time reduction can be achieved, for instance: by increasing the operation personnel, by upgrading the automation system, by communication system, among others.
5 Problem formulation
The distribution network planning problem based on OPF model must be able to evaluate the load distribution among substation, distributed generators and feeders. The result should meet demand and technical requirements (a feasible result).
In this paper, the optimisation problem is modelled as an MINLP. The model presented an objective function that represents the costs of future investments in order to reduce the repair time (minimisation of investment – Z1) as well as the reliability related costs, i.e. NSE costs (NSE costs – Z2). Also, it ensures the possibility of the optimal capacitors sizing in the network supporting the nodes voltage (injecting reactive power) and considers the substation transformer taps. Moreover, when this method is compared with the state‐of‐the‐art it considers a multi‐objective problem subjected to all technical constraints, as well as the constraints related with the repair time reductions using a deterministic process. Furthermore, the fuzziness uncertainty associated to repair times and failure rates is considered. Thus, this model represents an advantage regarding to the state‐of‐the‐art.
(11)
(12)
(13)-
Active and reactive power flow equations
(14)
(15) -
Selection of a unique value in each capacitor bank
(16) -
Reactive power output by capacitors
(17) -
Upper and lower power output limits (active and reactive powers) of the substation and distributed generator units
(18)
(19) -
Bus voltage magnitude limits
(20) -
Bus angle limits
(21) -
Capacity limits of distribution lines/cables
(22) -
Transformer taps limits
(23) -
Final repair time equation
(24) -
NSE threshold
(25) -
Only one investment option (action) can be picked for repair time
(26)
6 Case study
Tests were conducted in the 33‐bus distribution test network adapted from [23]. This test system is a hypothetical 12.66 kV system with two feeders, one substation, 33 buses, and 32 load points. The total substation load for this case study is 4549 kVA. Some adaptations were made in this network – two DGs units with 500 kW, 250 kVAr in buses 11 and 27; four capacitors sizes with 150, 300, 450, and 600 kVAr can be installed in buses 5 and 10; the substation transformer has a continuous value tap (±5%).
The 33‐bus distribution network (Fig. 3) does not have an outage database associated, thus the authors created an outage database (Table 1) in order to apply the proposed methodology.
| Bus out | Bus in | Mean time to repair – r, h | Number of interruptions | Time period, years | Average interruption rate – λ, interruptions/year | Unavailability – U, h/year |
|---|---|---|---|---|---|---|
| Lines or cables | ||||||
| 33 | 1 | 30.200 | 3 | 10 | 0.300 | 9.060 |
| 1 | 2 | 26.700 | 11 | 10 | 1.100 | 29.370 |
| 1 | 18 | 25.100 | 9 | 10 | 0.900 | 22.590 |
| 2 | 3 | 11.900 | 21 | 10 | 2.100 | 24.990 |
| 2 | 22 | 9.500 | 21 | 10 | 2.100 | 19.950 |
| 3 | 4 | 12.100 | 12 | 10 | 1.200 | 14.520 |
| 4 | 5 | 25.600 | 14 | 10 | 1.400 | 35.840 |
| 5 | 6 | 8.600 | 17 | 10 | 1.700 | 14.620 |
| 5 | 25 | 11.700 | 21 | 10 | 2.100 | 24.570 |
| 6 | 7 | 29.300 | 11 | 10 | 1.100 | 32.230 |
| 7 | 8 | 9.700 | 29 | 10 | 2.900 | 28.130 |
| 8 | 9 | 12.100 | 12 | 10 | 1.200 | 14.520 |
| 9 | 10 | 9.200 | 26 | 10 | 2.600 | 23.920 |
| 10 | 11 | 12.100 | 21 | 10 | 2.100 | 25.410 |
| 11 | 12 | 10.100 | 12 | 10 | 1.200 | 12.120 |
| 12 | 13 | 8.300 | 8 | 10 | 0.800 | 6.640 |
| 13 | 14 | 13.800 | 8 | 10 | 0.800 | 11.040 |
| 14 | 15 | 29.800 | 12 | 10 | 1.200 | 35.760 |
| 15 | 16 | 8.900 | 30 | 10 | 3.000 | 26.700 |
| 16 | 17 | 20.300 | 17 | 10 | 1.700 | 34.510 |
| 18 | 19 | 12. 000 | 15 | 10 | 1.500 | 18.000 |
| 19 | 20 | 25.500 | 14 | 10 | 1.400 | 35.700 |
| 20 | 21 | 25.000 | 11 | 10 | 1.100 | 27.500 |
| 22 | 23 | 11.000 | 21 | 10 | 2.100 | 23.100 |
| 23 | 24 | 9.400 | 17 | 10 | 1.700 | 15.980 |
| 25 | 26 | 9.300 | 14 | 10 | 1.400 | 13.020 |
| 26 | 27 | 9.300 | 16 | 10 | 1.600 | 14.880 |
| 27 | 28 | 27.000 | 21 | 10 | 2.100 | 56.700 |
| 28 | 29 | 20.600 | 25 | 10 | 2.500 | 51.500 |
| 29 | 30 | 11.800 | 16 | 10 | 1.600 | 18.880 |
| 30 | 31 | 9.500 | 26 | 10 | 2.600 | 24.700 |
| 31 | 32 | 9.300 | 14 | 10 | 1.400 | 13.020 |

Single‐line 33‐bus distribution network (adapted from [23])
For this case study only lines and cables were considered for the analysis, and it is assumed that the substation and DG units have 100% of availability.
The actions that the system operator can apply to reduce the repair time are the increase the operation personal (IOP), automation system upgrade (ASU), and communications upgrade (CUp).
Each one of these actions has a cost and results in a repair time reduction for each system component.
The NSE cost is 2 mμ/kVAh. A set of 1000 random weights is determined. A 10‐year lifetime project with a 1.75% discount rate, which leads to a 0.110 capital recovery factor, is considered for the NSE cost and investment in repair time reduction cost.
GAMS, with DICOPT solver, has been used to develop the weighted AC optimisation that uses MINLP. The MATLAB software has been linked with GAMS in order to solve the model to all 1000 weights. The way used to link GAMS to MATLAB can be found in [29]. For this case study, a computer with one processor Intel Xeon E3‐1225 3.20 GHz with four cores, 4 GB of random‐access‐memory (RAM), and Windows 8 Professional 64‐bit operating system was used.
The initial network data considered in this case study are presented in Table 2. The initial losses are obtained running a power flow for distribution networks based on the algorithm of Thukaram et al. [30]. Tables 3 and 4 present the network data and reduction times per action with cost, respectively.
| Network active load, kW | 3715.000 |
| Network reactive load, kVAr | 2300.000 |
| Initial NSE, kVAh/year | 545060.000 |
| Initial NSE cost, m.u./year | 1090121.000 |
| Bus out | Bus in | R, Ω | X, Ω | Active load, kW | Reactive load, kVar | Apparent load, kVA | Thermal limit, kVA |
|---|---|---|---|---|---|---|---|
| 33 | 1 | 0.0922 | 0.0470 | 100.0 | 60.0 | 116.619 | 450 |
| 1 | 2 | 0.4930 | 0.2511 | 90.0 | 40.0 | 98.489 | 450 |
| 2 | 3 | 0.3660 | 0.1864 | 120.0 | 80.0 | 144.222 | 450 |
| 3 | 4 | 0.3811 | 0.1941 | 60.0 | 30.0 | 67.082 | 329 |
| 4 | 5 | 0.8190 | 0.7070 | 60.0 | 20.0 | 63.246 | 450 |
| 5 | 6 | 0.1872 | 0.6188 | 200.0 | 100.0 | 223.607 | 329 |
| 6 | 7 | 0.7114 | 0.2351 | 200.0 | 100.0 | 223.607 | 329 |
| 7 | 8 | 1.0300 | 0.7400 | 60.0 | 20.0 | 63.246 | 329 |
| 8 | 9 | 1.0440 | 0.7400 | 60.0 | 20.0 | 63.246 | 329 |
| 9 | 10 | 0.1966 | 0.0650 | 45.0 | 30.0 | 54.083 | 329 |
| 10 | 11 | 0.3744 | 0.1238 | 60.0 | 35.0 | 69.462 | 329 |
| 11 | 12 | 1.4680 | 1.1550 | 60.0 | 35.0 | 69.462 | 329 |
| 12 | 13 | 0.5416 | 0.7129 | 120.0 | 80.0 | 144.222 | 329 |
| 13 | 14 | 0.5910 | 0.5260 | 60.0 | 10.0 | 60.828 | 329 |
| 14 | 15 | 0.7463 | 0.5450 | 60.0 | 20.0 | 63.246 | 229 |
| 15 | 16 | 1.2890 | 1.7210 | 60.0 | 20.0 | 63.246 | 329 |
| 16 | 17 | 0.7320 | 0.5740 | 90.0 | 40.0 | 98.489 | 329 |
| 1 | 18 | 0.1640 | 0.1565 | 90.0 | 40.0 | 98.489 | 329 |
| 18 | 19 | 1.5042 | 1.3554 | 90.0 | 40.0 | 98.489 | 329 |
| 19 | 20 | 0.4095 | 0.4784 | 90.0 | 40.0 | 98.489 | 329 |
| 20 | 21 | 0.7089 | 0.9373 | 90.0 | 40.0 | 98.489 | 450 |
| 2 | 22 | 0.4512 | 0.3083 | 90.0 | 50.0 | 102.956 | 450 |
| 22 | 23 | 0.8980 | 0.7091 | 420.0 | 200.0 | 465.188 | 450 |
| 23 | 24 | 0.8960 | 0.7011 | 420.0 | 200.0 | 465.188 | 450 |
| 5 | 25 | 0.2030 | 0.1034 | 60.0 | 25.0 | 65.000 | 450 |
| 25 | 26 | 0.2842 | 0.1447 | 60.0 | 25.0 | 65.000 | 329 |
| 26 | 27 | 1.0590 | 0.9337 | 60.0 | 20.0 | 63.246 | 329 |
| 27 | 28 | 0.8042 | 0.7006 | 120.0 | 70.0 | 138.924 | 329 |
| 28 | 29 | 0.5075 | 0.2585 | 200.0 | 600.0 | 632.456 | 329 |
| 29 | 30 | 0.9744 | 0.9630 | 150.0 | 70.0 | 165.529 | 329 |
| 30 | 31 | 0.3105 | 0.3619 | 210.0 | 100.0 | 232.594 | 329 |
| 31 | 32 | 0.3410 | 0.5302 | 60.0 | 40.0 | 72.111 | 329 |
| Bus out | Bus in | IOP, h | ASU, h | CUp, h | IOP, m.u. | ASU, m.u. | CUp, m.u. |
|---|---|---|---|---|---|---|---|
| 1 | 2 | 8.00 | 16.00 | 21.40 | 76,000 | 114,000 | 152,000 |
| 1 | 18 | 7.50 | 15.10 | 20.10 | 6400 | 9600 | 12,800 |
| 2 | 3 | 3.60 | 7.10 | 9.50 | 56,400 | 84,600 | 112,800 |
| 2 | 22 | 2.90 | 5.70 | 7.60 | 18,000 | 27,000 | 36,000 |
| 3 | 4 | 3.60 | 7.30 | 9.70 | 53,600 | 80,400 | 107,200 |
| 4 | 5 | 7.70 | 15.30 | 20.50 | 52,400 | 78,600 | 104,800 |
| 5 | 6 | 2.60 | 5.20 | 6.90 | 20,400 | 30,600 | 40,800 |
| 5 | 25 | 3.50 | 7.00 | 9.40 | 37,600 | 56,400 | 75,200 |
| 6 | 7 | 8.80 | 17.60 | 23.40 | 16,400 | 24,600 | 32,800 |
| 7 | 8 | 2.90 | 5.80 | 7.70 | 12,400 | 18,600 | 24,800 |
| 8 | 9 | 3.60 | 7.20 | 9.70 | 11,600 | 17,400 | 23,200 |
| 9 | 10 | 2.70 | 5.50 | 7.30 | 10,800 | 16,200 | 21,600 |
| 10 | 11 | 3.60 | 7.30 | 9.70 | 9600 | 14,400 | 19,200 |
| 11 | 12 | 3.00 | 6.10 | 8.10 | 8000 | 12,000 | 16,000 |
| 12 | 13 | 2.50 | 5.00 | 6.70 | 6800 | 10,200 | 13,600 |
| 13 | 14 | 4.10 | 8.30 | 11.00 | 3600 | 5400 | 7200 |
| 14 | 15 | 8.90 | 17.90 | 23.80 | 3200 | 4800 | 6400 |
| 15 | 16 | 2.70 | 5.30 | 7.10 | 2400 | 3600 | 4800 |
| 16 | 17 | 6.10 | 12.20 | 16.30 | 1600 | 2400 | 3200 |
| 18 | 19 | 3.60 | 7.20 | 9.60 | 4800 | 7200 | 9600 |
| 19 | 20 | 7.70 | 15.30 | 20.40 | 3200 | 4800 | 6400 |
| 20 | 21 | 7.50 | 15.00 | 20.00 | 1600 | 2400 | 3200 |
| 22 | 23 | 3.30 | 6.60 | 8.80 | 16,000 | 24,000 | 32,000 |
| 23 | 24 | 2.80 | 5.60 | 7.50 | 8000 | 12,000 | 16,000 |
| 25 | 26 | 2.80 | 5.60 | 7.50 | 36,400 | 54,600 | 72,800 |
| 26 | 27 | 2.80 | 5.60 | 7.50 | 35,600 | 53,400 | 71,200 |
| 27 | 28 | 8.10 | 16.20 | 21.60 | 34,800 | 52,200 | 69,600 |
| 28 | 29 | 6.20 | 12.40 | 16.50 | 32,400 | 48,600 | 64,800 |
| 29 | 30 | 3.50 | 7.10 | 9.40 | 8400 | 12,600 | 16,800 |
| 30 | 31 | 2.90 | 5.70 | 7.60 | 5600 | 8400 | 11,200 |
| 31 | 32 | 2.80 | 5.60 | 7.40 | 1600 | 2400 | 3200 |
| 33 | 1 | 9.10 | 18.10 | 24.20 | 84,800 | 127,200 | 169,600 |
Twenty‐nine non‐dominated solutions or plans were obtained by the weighted AC optimisation. The algorithm took around 4954 s (1.38 h) to compute the set of 1000 weighted solutions. Table 5 presents the obtained non‐dominated solutions, and the economic evaluation for each of those solutions. The signal ‘minus’ in the values of NSE benefit and final benefit represents the benefit for system operator. It is important to note that without any investment the value of NSE cost at the end of 10 years (lifetime project) would be 9,920,103 m.u.
| Plan | Investment cost, m.u. | NSE cost, m.u. | NSE benefit, m.u. | Final benefit, m.u. | Payback, years | I.R.R., % |
|---|---|---|---|---|---|---|
| 1 | 5,495,616 | 3,634,406 | −6,285,698 | −790,082 | 7.96 | 14.38 |
| 2 | 5,515,920 | 3,622,558 | −6,297,546 | −781,626 | 7.97 | 14.17 |
| 3 | 5,524,380 | 3,619,442 | −6,300,662 | −776,282 | 7.98 | 14.05 |
| 4 | 5,531,148 | 3,611,348 | −6,308,755 | −777,607 | 7.98 | 14.06 |
| 5 | 5,551,452 | 3,596,553 | −6,323,550 | −772,098 | 7.99 | 13.91 |
| 6 | 5,566,680 | 3,585,344 | −6,334,760 | −768,080 | 8.00 | 13.80 |
| 7 | 5,600,520 | 3,563,654 | −6,356,450 | −755,930 | 8.02 | 13.50 |
| 8 | 5,620,824 | 3,553,364 | −6,366,739 | −745,915 | 8.03 | 13.27 |
| 9 | 5,627,592 | 3,550,057 | −6,370,046 | −742,454 | 8.04 | 13.19 |
| 10 | 5,839,092 | 3,435,065 | −6,485,038 | −645,946 | 8.19 | 11.06 |
| 11 | 5,859,396 | 3,424,776 | −6,495,328 | −635,932 | 8.21 | 10.85 |
| 12 | 5,866,164 | 3,421,469 | −6,498,635 | −632,471 | 8.21 | 10.78 |
| 13 | 6,043,824 | 3,339,754 | −6,580,349 | −536,525 | 8.36 | 8.88 |
| 14 | 6,077,664 | 3,318,066 | −6,602,037 | −524,373 | 8.38 | 8.63 |
| 15 | 6,097,968 | 3,307,777 | −6,612,326 | −514,358 | 8.39 | 8.43 |
| 16 | 6,104,736 | 3,304,470 | −6,615,634 | −510,898 | 8.40 | 8.37 |
| 17 | 6,740,928 | 3,012,588 | −6,907,516 | −166,588 | 8.88 | 2.47 |
| 18 | 6,999,804 | 2,910,635 | −7,009,469 | −9665 | 9.09 | 0.14 |
| 19 | 7,086,096 | 2,877,304 | −7,042,800 | 43,296 | 9.16 | −0.61 |
| 20 | 7,201,152 | 2,835,734 | −7,084,370 | 116,782 | 9.25 | −1.62 |
| 21 | 7,358,508 | 2,778,242 | −7,141,862 | 216,646 | 9.38 | −2.94 |
| 22 | 7,410,960 | 2,759,358 | −7,160,746 | 250,214 | 9.42 | −3.38 |
| 23 | 8,091,144 | 2,573,350 | −7,346,753 | 744,391 | 10.02 | −9.20 |
| 24 | 8,317,872 | 2,511,792 | −7,408,311 | 909,561 | 10.22 | −10.94 |
| 25 | 9,752,688 | 2,137,593 | −7,782,510 | 1,970,178 | 11.40 | −20.20 |
| 26 | 10,355,040 | 1,982,614 | −7,937,490 | 2,417,550 | 11.87 | −23.35 |
| 27 | 10,970,928 | 1,837,392 | −8,082,711 | 2,888,217 | 12.35 | −26.33 |
| 28 | 11,349,936 | 1,788,978 | −8,131,126 | 3,218,810 | 12.70 | −28.36 |
| 29 | 11,512,368 | 1,782,840 | −8,137,264 | 3,375,104 | 12.87 | −29.32 |
Fig. 4 presents the set of non‐dominated solutions (plans), which are plotted as NSE cost versus investment cost.

Non‐dominated solutions or plans for the 33‐bus distribution system
The fuzzy satisfying decision method is used to select the preferred solution among non‐dominated solutions obtained in optimisation stage. The minimum and maximum values as well as the desirable reference levels are presented in Table 6.
| Investment | NSE | |
|---|---|---|
| maximum cost, m.u. | 11,512,500 | 9,920,103 |
| minimum cost, m.u. | 0 | 1,782,902 |
| reference level | 0.2 | 0.7 |
The maximum cost value for investment objective was determined considering the weight of investment equal to one and the weight of NSE equal to zero. The minimum value is considered equal to zero, i.e. without any investment in the network. Regarding to the NSE the maximum value is equal to the NSE value for the 10 years lifetime project without any investment. The minimum value is that one which corresponds to the weight equal to zero.
To specify the reference levels for each objective the trade‐offs shown in Fig. 4 can help the decision maker to choose reasonable reference values. For instance, in the investment objective, it is considered the last value where it is yet possible to obtain an I.R.R. positive, i.e. 6,999,804 m.u. (plan 18) and also the minimum value of investment in the network, i.e, 5,495,616 m.u. Thus, it is obtained(6, 999, 804 − 5, 495, 616)/(6, 999, 804 − 0) = 0.21. In the NSE objective, it is considered the maximum cost value (3,634,406 m.u.), which corresponds to the minimum value of investment in the trade‐off curve, and also the minimum cost (1,782,840 m.u.) in the same curve. So, it is obtained(9, 920, 103 − 3, 634, 406)/(9, 920, 103 − 1, 782, 840) = 0.77. Taking into account these values the reference levels for each objective are set to the ones presented in Table 4.
Applying the optimisation problem from (9) it is selected the solution of plan 1 (see Table 5).
Plan 1 presents the higher benefit (monetary units – m.u.) for the system operator (790,082 m.u.). The objective function value is of 9,130,022 m.u. for 10 years of project lifetime. Considering this plan, the payback presents a value of 7.96 years and the internal rate of return a value of 14.38%.
The values for final repair times can be found in Table 7. The zero in unavailability reduction means that the respective components do not have any investment action (in repair time).
| Bus out | Bus in | Final repair time – Fr, h | Interruption rate – λ, interruption/year | Final unavailability – U, h/year | Unavailability reduction – U, h/year | Unavailability reduction, % |
|---|---|---|---|---|---|---|
| Lines or cables | ||||||
| 33 | 1 | 30.200 | 0.300 | 9.060 | 0.000 | 0.000 |
| 1 | 2 | 5.300 | 1.100 | 5.830 | 23.540 | 80.150 |
| 1 | 18 | 5.000 | 0.900 | 4.500 | 18.090 | 80.080 |
| 2 | 3 | 11.900 | 2.100 | 24.990 | 0.000 | 0.000 |
| 2 | 22 | 1.900 | 2.100 | 3.990 | 15.960 | 80.000 |
| 3 | 4 | 12.100 | 1.200 | 14.520 | 0.000 | 0.000 |
| 4 | 5 | 5.100 | 1.400 | 7.140 | 28.700 | 80.078 |
| 5 | 6 | 3.400 | 1.700 | 5.780 | 8.840 | 60.465 |
| 5 | 25 | 11.700 | 2.100 | 24.570 | 0.000 | 0.000 |
| 6 | 7 | 5.900 | 1.100 | 6.490 | 25.740 | 79.863 |
| 7 | 8 | 9.700 | 2.900 | 28.130 | 0.000 | 0.000 |
| 8 | 9 | 12.100 | 1.200 | 14.520 | 0.000 | 0.000 |
| 9 | 10 | 9.200 | 2.600 | 23.920 | 0.000 | 0.000 |
| 10 | 11 | 12.100 | 2.100 | 25.410 | 0.000 | 0.000 |
| 11 | 12 | 2.000 | 1.200 | 2.400 | 9.720 | 80.198 |
| 12 | 13 | 3.300 | 0.800 | 2.640 | 4.000 | 60.241 |
| 13 | 14 | 2.800 | 0.800 | 2.240 | 8.800 | 79.710 |
| 14 | 15 | 6.000 | 1.200 | 7.200 | 28.560 | 79.866 |
| 15 | 16 | 1.800 | 3.000 | 5.400 | 21.300 | 79.775 |
| 16 | 17 | 4.000 | 1.700 | 6.800 | 27.710 | 80.296 |
| 18 | 19 | 2.400 | 1.500 | 3.600 | 14.400 | 80.000 |
| 19 | 20 | 5.100 | 1.400 | 7.140 | 28.560 | 80.000 |
| 20 | 21 | 5.000 | 1.100 | 5.500 | 22.000 | 80.000 |
| 22 | 23 | 2.200 | 2.100 | 4.620 | 18.480 | 80.000 |
| 23 | 24 | 1.900 | 1.700 | 3.230 | 12.750 | 79.787 |
| 25 | 26 | 9.300 | 1.400 | 13.020 | 0.000 | 0.000 |
| 26 | 27 | 9.300 | 1.600 | 14.880 | 0.000 | 0.000 |
| 27 | 28 | 5.400 | 2.100 | 11.340 | 45.360 | 80.000 |
| 28 | 29 | 4.100 | 2.500 | 10.250 | 41.250 | 80.097 |
| 29 | 30 | 2.400 | 1.600 | 3.840 | 15.040 | 79.661 |
| 30 | 31 | 1.900 | 2.600 | 4.940 | 19.760 | 80.000 |
| 31 | 32 | 1.900 | 1.400 | 2.660 | 10.360 | 79.570 |
Table 8 presents the optimised value for NSE when plan 1 is considered. The proposed methodology leads to a 36.6% reduction in the NSE value. For the considered plan only bus 5 has a capacitor bank with 600 kVAr. Regarding to the substation transformer tap, the obtained value is of 1.001 p.u.
| Initial value | Threshold value | Obtained value | |
|---|---|---|---|
| NSE, kVAh/year | 545060.000 | 200000.000 | 199690.000 |
Table 9 shows the chosen actions to be applied in the network components. The symbol ‘✓’ denotes that the respective action was chosen. It is possible to see that the automation system upgrade action was chosen for two components, while communications’ upgrade was chosen for 22 components.
| Bus out | Bus in | IOP | ASU | Cup |
|---|---|---|---|---|
| 33 | 1 | — | — | — |
| 1 | 2 | — | — | ✓ |
| 1 | 18 | — | — | ✓ |
| 2 | 3 | — | — | — |
| 2 | 22 | — | — | ✓ |
| 3 | 4 | — | — | — |
| 4 | 5 | — | — | ✓ |
| 5 | 6 | — | ✓ | — |
| 5 | 25 | — | — | — |
| 6 | 7 | — | — | ✓ |
| 7 | 8 | — | — | — |
| 8 | 9 | — | — | — |
| 9 | 10 | — | — | — |
| 10 | 11 | — | — | — |
| 11 | 12 | — | — | ✓ |
| 12 | 13 | — | ✓ | — |
| 13 | 14 | — | — | ✓ |
| 14 | 15 | — | — | ✓ |
| 15 | 16 | — | — | ✓ |
| 16 | 17 | — | — | ✓ |
| 18 | 19 | — | — | ✓ |
| 19 | 20 | — | — | ✓ |
| 20 | 21 | — | — | ✓ |
| 22 | 23 | — | — | ✓ |
| 23 | 24 | — | — | ✓ |
| 25 | 26 | — | — | — |
| 26 | 27 | — | — | — |
| 27 | 28 | — | — | ✓ |
| 28 | 29 | — | — | ✓ |
| 29 | 30 | — | — | ✓ |
| 30 | 31 | — | — | ✓ |
| 31 | 32 | — | — | ✓ |
7 Conclusions
A new methodology to reduce the NSE in a radial distribution network by identifying new investments is proposed in order to reduce the repair time in network components. To estimate the network outage parameter (which is a very important issue in the proposed method) a fuzzy set approach was used.
As a main contribution, an AC optimisation model based on MINLP was developed considering the Pareto front technique (weighted method) to achieve a reduction in repair times of distribution networks components, while minimising the costs of that reduction, as well as the NSE costs. The optimisation model proposed in this paper identifies the actions to be taken, as well as the components in which the system operator must invest at minimum cost. The model also considers the distribution network technical constraints, and it is able to consider the substation transformer taps and to choose the size of capacitor banks.
Regarding all the obtained plans (non‐dominated solutions) the system operator can carry out an analysis in order to choose a solution preference. Through the obtained results the proposed method proves to be adequate to support the distribution network operator to plan future network investment actions.
8 Acknowledgments
This work was supported by FEDER Funds through COMPETE program and by National Funds through FCT under the projects FCOMP‐01‐0124‐FEDER: UID/EEA/00760/2013, and PTDC/SEN‐ENR/122174/2010, and by the GID‐MicroRede, project no. 34086, co‐funded by COMPETE under FEDER via QREN Programme, and by the SASGER‐MeC, project no. NORTE‐07‐0162‐FEDER‐000101, co‐funded by COMPETE under FEDER Programme. The present work also developed under the EUREKA – ITEA2 Project SEAS with project number 12004.




